Temporary Connection and Relocation

When You’d Need a Temporary Connection

  • Construction of a house, building, or plaza
  • Weddings, festivals, exhibitions, political or religious gatherings
  • Testing industrial equipment
  • Any other short-term/emergency need

Construction Connections

Initially granted for 6 months, extendable in 3-month blocks until your project finishes. Apply on the standard new-connection form (Annex-I) with:

  • Ownership proof
  • If you’re not the owner: an affidavit from the owner (Rs. 50 stamp paper) accepting responsibility for dues
  • Attested CNICs (applicant, witness, and landlord if applicable)
  • For housing societies/high-rises: evidence your layout plan/NOC is at least in process

You’ll pay a Demand Notice covering connection charges plus a security deposit (based on your estimated usage during the connection period) – this is refunded or adjusted if you later convert to a permanent connection. Power is connected within 15 days of payment, on priority.

Events, Weddings & Testing

Granted for up to 2 weeks. You’ll need Annex-I, your CNIC, and payment of any applicable charges + security deposit. Political or public gatherings additionally require an NOC from the local administration (Deputy/Assistant Commissioner).

Extending, Ending, or Converting

  • Apply for extension at least 1 week before expiry if you still need it.
  • IESCO can disconnect without notice if the connection stops being genuinely "temporary" or gets misused.
  • After expiry, equipment is removed and its depreciated cost refunded to you – unless you convert to a permanent connection, in which case existing material is reused and your tariff switches to the applicable permanent rate.
  • Want to shift the setup to another location? IESCO can relocate it if the new site is within their territory, in your name (or a valid lease), all dues are cleared, and technical limits at the new site allow it. You’ll pay 10% of material cost for shifting plus any new material needed.

Bottom line: For weddings/events specifically, don’t forget the administration NOC if it’s a public gathering – that’s the step people miss most often.

Similar Posts

  • Understanding IESCO Tariff

    Understanding IESCO Tariff What "Tariff" Actually Means Your IESCO bill isn’t priced randomly – every rate you pay is approved by NEPRA (Pakistan’s electricity regulator) and officially notified by the government. IESCO cannot charge anything outside this approved schedule. If a rate on your bill ever looks off, you have the right to ask IESCO…

  • Violation of Instructions

    Violation of Instructions If IESCO Doesn’t Respond, or You’re Unhappy With the Outcome You’re not stuck. There’s a real escalation path once your original complaint doesn’t get resolved fairly: Provincial Office of Inspection (POI) – file here for issues around metering, billing, or tariff collection (under Section 38 of the Electricity Act). If you disagree…

  • Consumer Complaints

    Consumer Complaints Where to File a Complaint Any IESCO Consumer Services Center or the One-Window Operation desk at your local office. You’ll get an acknowledgement with a defined response timeline – these aren’t open-ended. Billing Complaint Timelines (Know Your Rights) Wrong meter reading or calculation error: resolved within 7 days Tariff dispute: within 30 days…

  • Metering Installation

    Metering Installation Where Your Meter Gets Installed Usually placed outside your premises, at a height reachable without climbing equipment. If it’s on your property, you’re responsible for its safe custody; if IESCO installs it on a pole/structure, that responsibility is theirs. Multi-occupant buildings get individually labeled meters per unit. If Your Meter Is Stolen or…